Requirements for dry transformer installation environment

Time:2023-8-7 15:46:56      Clicks:117

The dry type transformer carries on the accurate transmission and the transmission to the electric quantity, carries on the electric quantity uniform transmission. However, dry transformer must be installed according to relevant conditions in the installation, so as to ensure the normal operation of dry transformer. Jiangsu Evergrande transformer co., LTD. The following to understand the dry transformer installation environment requirements.
Requirements for dry transformer installation environment:
1. The installation site of dry power transformer shall meet the environmental requirements of the manufacturer. The room shall be clean, without other penetration facilities of non-building structure, and the roof shall not leak.
2. The infrastructure meets the requirements of load, shock prevention and bottom ventilation.
3. Indoor ventilation and fire fighting facilities are in line with relevant regulations. Ventilation ducts are well sealed and ventilation holes are not connected with other ventilation systems.
4. The temperature control and temperature display devices are located in obvious positions for easy observation.
5. The door of the room is made of non-combustible or refractory materials, with the door opening outwards. The name of the equipment and safety warning mark are marked on the door.